Configure Dock
Job
Lower Dock
Gangway
Upper Structure
Decking + Finish
Estimator Snapshot
Lower dock
32 × 32
ft
Gangway
4 × 40
one continuous frame
Upper deck
20 × 29
ft
Decking pad
5%
composite + PT 2×4
Configuration passes the currently confirmed geometry checks.
Live Dock Layout
Current build logic
Full-length finger/frame
Head section
Upper deck
Gangway
Gangway defaults to the exact dock centerline. Lower and upper deck boards run side-to-side; PT 2×4 runners run perpendicular.
PRICE CALIBRATION IN PROGRESS
Estimator engine
This demo intentionally does not present a “final sell price” yet. Material formulas, labor formulas, current SKU costs, and benchmark reconciliation are still being locked down before live use.
| Module | Size | Estimator / CAD note |
|---|
Composite stock lengths: 12', 16', and 20'. Final production cut plan will optimize actual run lengths around slips; useful 3' drops may be used for stairs, but the base estimate does not depend on offcut reuse.
Lower deck board directionSide-to-side
Upper deck board directionSide-to-side
Gangway board directionAcross 4' width
PT 2×4 directionPerpendicular to decking
Gangway width4' fixed
Gangway default positionCentered
Stair-side head section6' minimum
Standard stair3' wide • 19 treads
Upper roof surfaceSheet metal under entire upper deck
Material cushion5%